Take place via VRVS - FOG virtual room
    • 10:30 10:40
      Progress with 2.7.0 upgrades 10m
      - Review of individual site progress and plans to upgrade. - Problems and experiences to be fed back to the CERN deployment team
      Speaker: Jeremy
      more information
    • 10:40 10:50
      Highlights from the pre-CHEP Service Challenge workshop! 10m
      - Experiment planning and expectations - Agreed functionality - Issues with the SRMs
      Speaker: Jeremy/Alessandra/Graeme/Greig
      document
      more information
    • 10:50 11:00
      Deployment plans for gLite 3.0 10m
      - The current planning for the next release after 2.7.0 which is named gLite 3.0 - What functionality will be in gLite 3.0 - Requirements for SC4
      Speaker: Jeremy
      transparencies
    • 11:00 11:15
      An update on GridPP preparation for SC4 15m
      - What have we achieved so far - What problems are being experienced that are likely to impact other sites moving forward - What is the timeline for future tests (see: http://wiki.gridpp.ac.uk/wiki/Service_Challenge_Transfer_Tests) - Other than achieveing throughput rates what are our objectives - Planning to get more sites involved/further developed (go here to find out what is involved: http://wiki.gridpp.ac.uk/wiki/Transfer_Test_Checklist)
      Speaker: Deployment team
    • 11:15 11:25
      Network monitoring boxes 10m
      - A reminder of what the network monitoring boxes announced on TB-SUPPORT are for - Are there any issues with site security policies? - Information that is required to install/deliver them - Specific requests to sites - Q&A
      Speaker: Robin Tasker?
    • 11:25 11:30
      AOB 5m
      - Advance notice of the SC4 Tier-2 tutorials and workshop to be held at CERN during the week of 12th June. Please see draft agendas: http://indico.cern.ch/conferenceDisplay.py?confId=1148 & http://indico.cern.ch/conferenceDisplay.py?confId=a058483 - Phasing out of SL3 scheduled for October 2006 - Sites should check that they are publishing "memory per job slot" not total memory.